Paul & Marieke’s house renovation in Rijsbergen — Part 3: Ground floor

  • Openings and steel supports
  • Opening the floor and adapting services
  • Two insulation layers and a heated floor
  • Finishing walls and connections

The third stage focuses on the ground floor: a more open layout, renewed services and an insulated floor with underfloor heating.

Project timeline

October 2026–January 2027 · Planned

Before & after

Before

Photos coming soon

After

Photos coming soon
Paul & Marieke’s house renovation in Rijsbergen — Part 3: Ground floor

The existing rooms need to connect more naturally. This combines structural openings with work that will later sit beneath the new floor and behind the walls. This stage is planned to start in late October 2026.

This story describes the planned work. The final result will be added when confirmed.

02 / Step by step

The project in phases

Phase 1

Structural Demolition & Beam Installation

The planned ground-floor openings require temporary support and the specified steel beams. Structural work must follow the engineer’s design before the rooms can be opened into one another.

We will prepare the work areas and temporarily support the load-bearing structure according to the structural plan. The agreed wall openings and steel beams follow. New openings connect the living spaces, with final beams and bearings following the engineer’s drawings.

This third stage is planned around a different ground-floor layout. Opening load-bearing walls changes how forces pass through the house, so the steelwork and its supports follow the structural design. Temporary support belongs to that construction phase before the openings become part of the interior.

The aim is to connect the living areas while coordinating those new passages with doors, floors and service routes. The work described here remains planned.

Why this matters

A wider opening changes how loads are carried. Temporary support and permanent beams belong to the same phase.

Phase 2

Ceiling Demolition (Kitchen Area) & New Door Openings

The kitchen ceiling and old insulation will be opened separately from the structural wall phase. Existing door and window positions are prepared for the revised openings.

Phase 3

Floor Demolition, Clearing & Excavation

Old flooring and heating pipes will be removed where included, then the base excavated for the new build-up. The conservatory floor strip-out was removed from the updated scope.

Old floor layers will be removed in the agreed work areas. Water and electrical routes can then be prepared for the new layout. The kitchen receives appliance and induction-hob connections. The excluded conservatory floor area will not undergo the same strip-out.

Removing the agreed old floor layers makes the service routes accessible before the new insulated floor is built. Kitchen appliance and induction connections are part of the new layout, with water and electrical provision prepared in advance of the finishes.

The conservatory floor is excluded from the same strip-out. This distinction matters when describing the project: adjoining rooms can belong to the wider home without receiving an identical new floor construction.

Why this matters

An open floor allows services to be routed before the new finish covers them.

Phase 4

Plumbing & Radiator Pipework

Existing radiator and plumbing routes will be adapted to the new layout. This remains distinct from the floor-heating installation, including the retained heating requirement for the study.

Phase 5

Electrical Installation (Full Replacement)

The electrical package provides the new cable routes, outlets, switches and lighting connections. These positions are coordinated with the kitchen and room layout before closing the walls.

Phase 6

Insulation & Underfloor Heating Installation

The planned floor has two 100 mm PIR layers and eleven heating circuits. Insulation continuity and edge details need to be established before the screed is placed.

The new build-up includes a prepared sand base, membrane, two 10 cm PIR layers, reinforcement and water-based underfloor heating. Heating distribution is planned around an eleven-circuit manifold. The study retains radiator heating. Screed and preparation for the floor finish follow.

The proposed two 10 cm PIR layers give the floor a substantial insulated build-up. Above this, reinforcement and heating pipes are combined with the screed. The eleven-circuit manifold distributes the planned floor-heating system, while the study retains its radiator.

Finished height is a shared consideration across this sequence: sand base, membrane, insulation, heating and final floor all contribute. Door and room transitions therefore belong to the planning before the layers are installed.

Why this matters

Heating and insulation are planned together as parts of the complete floor system.

Phase 7

Cement Screed & Leveling

The screed is a separate phase after the pipes and insulation. Its levels and drying condition determine when the floor can receive its final smoothing and finish.

Phase 8

Exterior Wall Insulation & Drywall Construction

Insulated wall linings and the new partitions will be framed and boarded. Junctions with windows, doors and service routes are coordinated before plastering.

Phase 9

Fireplace System Installation

The offer includes the fireplace flue route and its fire-safe detailing as a separate stage. The selected appliance and actual site conditions determine the final connection arrangement.

Phase 10

Plastering Walls & Ceilings

The new and retained surfaces will be prepared, reinforced where required and plastered. The work brings the altered walls and ceiling areas into a consistent finish.

We will insulate and line the agreed exterior-wall areas and form new partitions and service boxes where needed. Plastering follows. Planned doors include a kitchen sliding system, steel-and-glass doors and a glazed door in the new hall.

Exterior-wall insulation and new linings will connect to the altered floor and room layout. Service boxes conceal the necessary routes, while plastering creates the surfaces around the new doors and openings. The different door types give each connection its intended function.

Steel-and-glass doors, the kitchen sliding system and the glazed hall door are distinct planned elements. Their dimensions and junctions influence the construction around them.

Why this matters

Wall thicknesses, doors and service boxes need to fit together to avoid awkward finishing junctions.

Phase 11

Floor Smoothing & Vinyl Installation

The ground-floor finish is click-PVC, distinct from the clients’ wooden flooring upstairs. The specified smoothing and underlay belong to this phase after the screed is ready.

The ground floor is planned to receive click-PVC flooring, underlay and skirting. This is separate from the wooden upstairs floor the owners will install themselves. Work is expected to start in late October 2026 and finish in late January 2027.

Click-PVC, underlay and skirting form the planned finish downstairs. This differs from Part 2, where the owners chose to lay their own wooden finish upstairs. Keeping those two arrangements separate avoids presenting the whole house as one identical flooring package.

The revised programme runs from late October 2026 to late January 2027. The intended result is a connected ground floor with renewed services, insulation, heating and finishes.

Why this matters

Planning the three parts separately keeps the work sequence and the owners’ own tasks clear.

Phase 12

Doors, Windows & Final Assembly

Interior and sliding doors, the conservatory connection and window details close the planned package. The revised project period runs from late October 2026 to late January 2027.