Phase 1
Preparation & Protection
The existing upper floor and access routes were prepared for the room conversion and bathroom work.
HWR / THE TRANSFORMATION
Explore the transformation. Choose a chapter, swipe through the details, or open the photo wall.
We are collecting the images for this stage.
Swipe to explore · Tap full screen for the details
Poeldijk / Ongoing
An upper floor in Poeldijk is becoming two bedrooms and a bathroom, with light storage above the new ceiling.
September–October 2026 · Expected completion in October
Radu and Marinela wanted to make better use of the available space and height. Existing floor heating needed care around the new partitions, while the bathroom and floor choices evolved during the project.
02 / Step by step
Phase 1
The existing upper floor and access routes were prepared for the room conversion and bathroom work.
Phase 2
A new ceiling and overhead storage space were planned together. The space above is storage, not an additional habitable room.
We are building partitions with stone wool and double boarding, plus a new ceiling with light storage above. The junction with the existing heated floor is carefully prepared. The upper space is storage, not an additional habitable floor.
Radu and Marinela’s upper floor is being divided into two bedrooms and a bathroom, with storage above the new ceiling. The partitions use a cavity with stone wool and double boarding. The ceiling separates the rooms from the storage volume above, giving the tall existing space a different layout.
The junction at the existing heated floor needs particular attention during partition work. The room arrangement, door positions and available storage height all belong to the same conversion.
The partitions need to suit the existing floor and the intended use of the rooms.
Phase 3
The two interior door openings and frames belong to their own joinery stage, coordinated with the new room divisions.
Phase 4
The partition separates the rooms with a framed, layered construction. Junctions and service routes matter as much as the board faces for limiting sound paths.
Phase 5
Changed finish: the original PVC proposal was replaced by click laminate. The revised scope also includes rebuilding the second bedroom floor.
Phase 6
The new toilet drainage route is coordinated with the existing structure and acoustic enclosure. The revised arrangement uses an accessible AAV instead of the originally proposed roof vent route.
Phase 7
New water routes and the electric boiler serve the upstairs bathroom, with connection positions coordinated before closing the structure.
Phase 8
Room ventilation connects to the existing duct arrangement. This is separate from the AAV used to admit air into the drainage system.
Phase 9
Dedicated connections for the boiler, washing machine and dryer are coordinated with the changed equipment positions, alongside room lighting and sockets.
The flooring choice changed to click laminate, with the second bedroom floor also being redone. New circuits are provided for the water heater and dryer, while the washer connection moves. Remaining waterproofing, tiling, plaster and paint finishes follow the service work.
The switch to click laminate and the additional bedroom floor work changed the finishing package. Electrical changes include dedicated provision for the water heater and dryer and a relocated washing-machine connection, so the rooms and appliances can be arranged around the new layout.
Work then moves from services into waterproofing, tiling and surface finishing. Keeping the final flooring and paint towards the finishing stage helps connect the new partitions, bathroom and bedroom areas visually.
Incorporating changes during preparation helps the finishes match the final layout.
Phase 10
The updated bathroom has a 170 × 70 cm bathtub and niche instead of the original walk-in-shower proposal. Water, drainage, waterproofing and finishes must follow that revised layout.
The original walk-in shower was replaced in the plan by a 170 × 70 cm bathtub and a niche. We are adapting water and waste lines and preparing the sanitary connections. Drain ventilation uses an air-admittance valve; room ventilation connects to the existing duct.
The revised bath-and-niche layout changes more than the sanitary item itself. It affects the wall finish, connection positions and the way the bathroom is used. Pipe routes are being adapted to that revised arrangement before the waterproof and tiled surfaces are finished.
The air-admittance valve serves the drainage system, while the existing ventilation duct serves room ventilation. They have different purposes and should not be confused, even though both are part of the bathroom’s hidden services.
A different bathroom layout changes the positions of the hidden services too.
Phase 11
The new walls and ceiling junctions receive the specified plaster and fine finishing before decoration.
Phase 12
Painting remains a separate stage after surface preparation and drying.
Phase 13
Transport, waste handling, installation checks and final handover form the closing stage of the September–October 2026 work.
Your renovation
Tell us about your home and your ideas. We will discuss the scope and the next step with you.

April–May 2026
Explore this project
May 2025
Explore this project
June 2026 — proposed work month in the offer
Explore this project