Ridderkerk / Completed

Radjen’s house renovation in Ridderkerk

  • Identifying the ceiling problem
  • Removing boards and rebuilding the framing
  • Floors, four bathrooms and two toilets
  • Plastering and work beyond the living rooms

Finishing a newly built home with tiled floors, four bathrooms and two toilets. During preparation, we discovered a problem overhead: the ceiling boards moved at their joints.

Project timeline

October–November 2025

Before & after

Radjen’s house renovation in Ridderkerk — After renovationRadjen’s house renovation in Ridderkerk — Before renovationBeforeAfter
Radjen’s house renovation in Ridderkerk

The original scope covered tiling throughout the home, four bathrooms with walk-in showers, two toilets, and plastering walls and ceilings. But many edges of the existing ceiling boards had no supporting framing underneath. Pressing them made adjacent boards bend independently. Plastering over them would hide the problem while leaving movement that could later crack the joints.

02 / Step by step

The project in phases

Phase 1

Floor & Wall Tiling

The tiling package covers the house floors and the wet-area walls, with client-supplied formats coordinated across four bathrooms and two toilets.

Tiling followed across the home’s floors and the four bathrooms with walk-in showers and two toilets. Walls in the wet areas were tiled too. The different tile formats were set out by room, with attention to corners, junctions and cuts.

Four bathrooms and two toilets made this a substantial wet-room finishing package. Each space combines a floor layout with wall tiles, openings and sanitary connection points. The walk-in shower areas also bring different surfaces together at corners and around drains.

Across the rest of the house, the tiled floors created a larger connected finish. Setting out a pattern in one room is only part of the work: doorways, visible cut pieces and the transition to neighbouring spaces influence the result too.

Why this matters

A layout plan connects the main floor areas with the smaller, more detailed wet rooms.

Phase 2

Wall & Ceiling Plastering

The walls and ceilings receive smooth plaster and a fine finish. The unstable ceiling boards discovered at the start had to be corrected before this finish could be reliable.

Phase 3

Wall Reinforcement

The offer specifies reinforcement mesh across the blockwork walls beneath the plaster to help control cracking at vulnerable transitions.

Phase 4

Bathroom & Toilet – Moisture-Resistant Ceilings

Wet-room ceilings have their own protective coating specification, separate from the wall and floor tiles.

Phase 5

Corner Reinforcement

Corners and junctions were reinforced with the specified profiles and mesh before their final finish.

Phase 6

Protection, Transport & Cleanup

Masking, material handling, waste removal and final cleaning support the finishing work throughout the house.

Additional work 1

Ceiling Removal & Frame Reconstruction

Approximately 240 m² of ceiling boards lacked support at their edges. The team removed the boards and rebuilt the framing around the board dimensions so the joints could be secured firmly.

During preparation, we found that the plasterboard edges could tilt and bend. Timber or metal supports were missing beneath their junctions. We decided to repair the base across approximately 240 m² of ceiling before continuing with plastering.

Radjen’s home was newly built, so the initial brief centred on tiling and plastering. The ceiling defect changed that sequence. Pressing at the unsupported board edges made adjacent sheets move relative to one another; a smooth plaster layer over that base would still be exposed to movement at the joints.

The issue was hidden behind what appeared to be a nearly finished ceiling. We therefore treated it as a construction problem to resolve before decoration, across roughly 240 m², rather than as a small surface repair.

We removed the boards and reinforced and rearranged the timber and metal framing. Its layout matched the boards: approximately 60 cm between support lines, with support at the 244 cm board ends. This allowed the edges to be fixed firmly to the frame. We allocated four to five working days to this repair.

Rebuilding the support layout meant the board joints could sit on framing rather than meet over an empty space. Both the long edges and the board ends needed support. The approximately 60 cm and 244 cm dimensions describe the layout used for these boards on this project, not a universal prescription for every ceiling.

This additional work was given a four-to-five-day working allowance. It added an important intermediate step: remove, reinforce and refix first, then continue towards the plaster finish.

Why this matters

Supported edges limit movement between adjacent boards, reducing the risk of cracks in the finish.

Additional work 2

Garage Plastering & Plant-Area Tiling

The detached garage plastering and the tiled zone around the heating and sanitary equipment were added beyond the original house-finishing package.

With the ceiling boards securely supported, the walls and ceilings could be plastered. The work expanded to include plastering the detached garage and tiling the area for the heating and plumbing systems, extending the finishes into the practical spaces.

The detached garage was added to the plastering work, while the heating and sanitary equipment zone received tiling. These additions extended the project beyond the rooms visitors see first. Practical areas benefit from considered finishes as well as living spaces.

The most important change in the story remains the ceiling repair. The work in October–November combined the originally requested finishes with correction of the substrate that those finishes depended on.

Why this matters

A garage and utility area also benefit from a practical, well-finished surface.